Mainland China’s data center market is evolving rapidly. As investors and developers invest/further invest, there are many themes, topics, and issues to consider. In our report we look at four key points and they are:
 
  • The market
  • Government policy
  • Investment
  • Environmental sustainability
 
The Market
 
At the beginning of 2021, cabinet stock in mainland China touched 3.6 million, with the anticipation that this number will surpass 4 million by the end of the year/beginning of 2022.
 
The Beijing-Tianjin-Hebei region, the Yangtze River Delta region and the Pearl River Delta region continue to maintain strong data center construction impetus, both in terms of the number of new cabinets and aggregate inventory.
 
Government Policy
 
One of the most important data center industry-related policies released recently in mainland China is The Three-year Action Plan for New Data Centre Development (2021-2023). The basic actions of the plan are:
 
  • Optimization of construction layout
  • Upgrading of network quality
  • Enhancement of computing power
  • Strengthening of the industrial chain
  • Green and low-carbon development
  • Safety and reliability
 
Investment
 
Domestic data center financing conduits in mainland China are varied. They are largely split into equity financing and debt financing, including public offering, rights issue, private placement, bond financing, bank loans and other instruments. 
 
Given the appealing cap rate that data center projects can offer, many investors of late have paid much attention to data center properties in China. These investors have executed on investment deals via a number of methods, such as directly purchasing data center property assets, forming a joint venture company, or utilizing financing channels. 
 
Sustainability
 
In the face of global warming, mainland China has propositioned the strategic goal of "reaching a carbon peak by 2030 and going carbon neutral by 2060." Data centers, on the other hand, transform electricity into computing power, and so with the swift growth of digital demand, data centers are progressively requiring a greater amount of electricity for center operational purposes.

Related Insights

2026-fit-out-cost-guide-hero-mobile-apac-750x456
Insights • Workplace

Office Fit Out Costs in New Zealand 2026

A collaborative hybrid office fit out in Auckland averages NZ$3,261 per sqm. While regional fit out cost growth has moderated, organisations continue to navigate potential pressure from labour, materials, energy costs and global supply chain disruption.

21/10/2026
HCMC office.png
Research • Economy

TOD: From Real Estate Value Growth to Greater Urban Productivity

TOD should not be viewed simply as a catalyst for rising land values around transit stations. Its broader purpose is to improve accessibility, use urban land more efficiently, and strengthen productivity.
Ngoc Le • 02/10/2026

Related Stories

UKG Sydney webcard
UKG Australia • HR Technology
Cushman & Wakefield acted as Principal Contractor for UKG Australia's new Sydney office, leading design development, procurement and construction from end to end. The project was delivered on time and within budget, with a reconfigured workspace, a feature green wall and a fully integrated technology setup.
Learn More
Auckland Prison Web card.png
Auckland Prison • Government / Justice & Corrections
Cushman & Wakefield provides integrated facilities and asset management services for Auckland Prison under a long-term PPP contract. Through proactive maintenance and refurbishment delivery, we help ensure safe, secure and reliable operations within a high-security correctional environment.
Learn More

CAN'T FIND WHAT YOU'RE LOOKING FOR?

Get in touch with one of our professionals.
With your permission we and our partners would like to use cookies in order to access and record information and process personal data, such as unique identifiers and standard information sent by a device to ensure our website performs as expected, to develop and improve our products, and for advertising and insight purposes.

Alternatively click on More Options and select your preferences before providing or refusing consent. Some processing of your personal data may not require your consent, but you have a right to object to such processing.

You can change your preferences at any time by returning to this site or clicking on Privacy & Cookies.
MORE OPTIONS
AGREE AND CLOSE
These cookies ensure that our website performs as expected,for example website traffic load is balanced across our servers to prevent our website from crashing during particularly high usage.
These cookies allow our website to remember choices you make (such as your user name, language or the region you are in) and provide enhanced features. These cookies do not gather any information about you that could be used for advertising or remember where you have been on the internet.
These cookies allow us to work with our marketing partners to understand which ads or links you have clicked on before arriving on our website or to help us make our advertising more relevant to you.
Agree All
Reject All
SAVE SETTINGS